Linwood: Consultation

We are currently in the pre-planning application stage of our work, meaning that a Proposal of Application Notice (PoAN) has been submitted to Renfrewshire Council informing them of our intention to undertake Pre-Application Consultation with key stakeholders and the local community, prior to submitting a full planning application to build our tyre processing plant in Linwood.

Having submitted our PoAN, we are now undertaking the statutory minimum 12 weeks of consultation and engagement with the local community, and we are keen to hear your thoughts on the plans, and to answer any questions you might have about our application and the proposed development.

As part of our consultation process, a virtual town hall event took place on Saturday March 20th between 10am – 12pm, during which members of the public were able to learn more about the plans and ask questions. A recording of this event can be found below.

Alternatively, if you have any questions or wish to understand more about the proposed you can also ask any questions using our online form.

Timeline

March 2021

Consultation Period 

March 2021
April 2021

Planning Application Submitted

April 2021
Late Summer 2021

Anticipated Determination 

Late Summer 2021
Autumn 2021

Commence Enabling Works 

Autumn 2021
Spring 2022

Start On Site 

Spring 2022
Autumn 2023 / Spring 2024

Projected Operational Commencement 

Autumn 2023 / Spring 2024